ClientHewlett Packard (ISS Facility Services)
-
ProjectHewlett Packard Chilled Water Upgrade
-
LocationIreland
-
M&E Value€ 3.0M
Project Summary
Upgrade of existing site wide chilled water system including replacement Cooling Towers, pipework and BMS controls modifications.
Project Duration: 18 months
Completion Date: 2017
Service Features:
- Replace 4No existing 3.75MW cooling towers with new
- Replace existing pumpsets with new
- Enabling and strip-out works
- Pipework modifications
- BMS controls modifications and recommissioning